June 11, 2025
Mr. Stauber introduced the following bill; which was referred to the Committee on Transportation and Infrastructure
To amend the Federal Water Pollution Control Act with respect to the period during which areas may be prohibited from being specified as disposal sites for dredged or fill material, and for other purposes.
Section 1. Short title
This Act may be cited as the Reducing Permitting Uncertainty Act
.
Sec. 2. Reducing permitting uncertainty
(a) In general
Section 404(c) of the Federal Water Pollution Control Act (33 U.S.C. 1344(c)) is amended—
(1)
by striking (c) The Administrator
and inserting the following:
(c) Specification or use of defined area
(1) In general
The Administrator;
(2)
in paragraph (1), as so designated, by inserting during the period described in paragraph (2) and
before after notice and opportunity for public hearings
; and
(3)
by adding at the end the following:
(2) Period of prohibition
The period during which the Administrator may prohibit the specification (including the withdrawal of specification) of any defined area as a disposal site, or deny or restrict the use of any defined area for specification (including the withdrawal of specification) as a disposal site, under paragraph (1) shall—
(A)
begin on the date on which an applicant submits all the information required to complete an application for a permit under this section; and
(B)
end on the date on which the Secretary issues the permit.
(b) Applicability
The amendments made by subsection (a) shall apply to a permit application submitted under section 404 of the Federal Water Pollution Control Act (33 U.S.C. 1344) after the date of enactment of this Act.